New Project (20)

Differences Between Chinese and Vietnamese Construction Standards: Three Common Pitfalls for Chinese Enterprises Building Factories in Vietnam

Differences Between Chinese and Vietnamese Construction Standards: Three Common Pitfalls for Chinese Enterprises Building Factories in Vietnam

donghui
14:14 - 07/01/2026
6 minutes of reading

From “Being Able to Build” to “Being Able to Operate in Compliance”:

Front-load risks, front-load approval timelines, and front-load first-pass acceptance

I. Executive Overview: Why Do “Standards Disparities” Lead to Work Suspension and Penalties?

When investing in factory construction in Vietnam, project failure is rarely caused by “poor construction execution”, but rather by a break in the regulatory compliance chain.

Many enterprises continue to apply mature domestic practices—finalizing designs first, mobilizing construction teams early, and handling approvals in parallel or retroactively. In Vietnam, however, such practices can directly trigger mandatory work suspension.

The fundamental reason lies in the fact that Vietnam’s standards system (QCVN/TCVN) is tightly bound to its approval logic (fire safety, environmental protection, construction permits). Any deviation at one stage will surface cumulatively during final acceptance, resulting in rework, schedule overruns, and cash-flow pressure.

Dong Hui recommends treating the project’s “first mile” as a manageable delivery chain:

Concept planning – standards verification – permitting – procurement – construction – documentation – acceptance, with each stage fully aligned.

II. Breakdown of the Three Major Pitfalls (High Frequency – Trigger Mechanism – Resolution Path)

Pitfall 1: Fire Safety Regulations (QCVN 06) — Do Not Directly Copy Chinese Drawings

This is currently the most common risk source, frequently leading to secondary modifications, demolition and rework, and prolonged work suspension.

1) Common Misconceptions

  • Assuming that fire compartments, fireproof coatings, and smoke extraction systems approved in China can be directly applied in Vietnam.

  • Design drawings meet production and investor requirements, but do not align with Vietnam’s fire approval criteria or material certification evidence chain.

2) Trigger Mechanisms (Why Projects Get Rejected)

  • Key materials must be supported by test and inspection reports recognized by Vietnamese authorities; incomplete evidence chains will require supplementation or replacement.

  • Differences exist in calculation logic for smoke extraction and evacuation (opening areas, evacuation distances, compartmentation), and any deviation will be deemed “non-compliant”.

  • Design review is strongly bound to on-site acceptance; if construction proceeds first and adjustments are made later, cost and schedule losses will multiply.

3) Dong Hui’s Resolution Path (One Design, One Approval)

  • Conduct fire safety compliance verification at the design stage, identifying and locking critical red-line parameters.

  • Establish a material compliance list (evidence chain) and confirm local certification and testing pathways prior to procurement.

  • Integrate approval strategy, testing plan, and on-site milestones into a single plan, targeting zero secondary demolition or rework.

References: QCVN 06:2022/BXD and Amendment 1:2023 (Circular 09/2023/TT-BXD); Decree 136/2020/ND-CP and its amendments (e.g., Decree 50/2024/ND-CP).

Pitfall 2: Geotechnical Investigation and Foundation Design — Underestimated Soft Soil and Settlement Risks

Soft soil is widely distributed in Vietnam’s northern plains and southern deltas. A factory that “can be built” does not necessarily guarantee stable long-term operation.

1) Common Misconceptions

  • Insufficient investigation depth and borehole density, with foundation decisions made based on experience rather than data.

  • Directly applying pile types, pile caps, or ground improvement solutions from domestic projects, while ignoring differences in settlement behavior and load combinations under TCVN.

2) Risk Trigger Mechanisms

  • Settlement exhibits a time-dependent effect, gradually manifesting after commissioning, leading to cracking, door and window deformation, equipment leveling difficulties, and production line instability.

  • Failure to verify against TCVN standards often results in two extremes: overly conservative designs with cost overruns, or insufficient structural safety posing operational risks.

3) Dong Hui’s Resolution Path (Converting Settlement Risk into Controllable Cost)

  • Prepare a detailed geotechnical investigation ToR, increasing investigation density at critical areas such as heavy-load zones, equipment areas, logistics routes, and fire water tanks.

  • Re-verify foundation schemes using TCVN parameter systems, producing calculation packages that are auditable and traceable.

  • Optimize ground treatment and structural solutions in an integrated manner, targeting lifecycle cost optimization and avoiding excessive conservatism.

Pitfall 3: Completion Acceptance and Compliance Documentation — “Build First, Legalize Later” Does Not Work in Vietnam

Vietnam’s regulatory process is a rigid, linear compliance chain. Missing procedures cannot be rectified retroactively and will be blocked at critical milestones.

1) Common Misconceptions

  • Believing construction can start before completing Environmental Impact Assessment (EIA) or obtaining construction permits.

  • Failing to manage process documentation in accordance with governmental archiving requirements, resulting in missing inspection records, variation approvals, or test reports.

2) Trigger Mechanisms (Why Projects Are Suspended or Certificates Denied)

  • Without approved EIA and fire safety design approval, construction permits are typically not issued; unauthorized commencement often results in work suspension and rectification orders.

  • Incomplete completion documentation prevents acceptance and registration, further affecting asset certification, financing collateralization, and future expansion approvals.

3) Dong Hui’s Resolution Path (Managing the “Documentation Chain” as a Deliverable)

  • Establish a master control plan with mandatory permitting milestones—EIA, fire design approval, construction permit, staged acceptance—embedded in the overall schedule as preconditions for commencement and payment.

  • Implement full lifecycle document version control and signature/seal closure, delivering a ready-to-submit as-built dossier.

  • Conduct pre-acceptance compliance reviews, closing gaps via checklist management to avoid repeated submissions.

References: Environmental Protection Law (2020); Decree 08/2022/ND-CP; Decree 15/2021/ND-CP.

III. Enterprise Self-Check List: Front-Loading Risks to the Tender / Concept Stage

Enterprises are advised to complete the following mandatory checks prior to concept confirmation, minimizing uncontrollable downstream risks.

Module Key Checkpoints Common Gaps Responsibility (RACI)
Fire Safety (PCCC) Fire compartmentation; fire resistance limits; smoke extraction and evacuation parameters; material evidence chain Materials lacking Vietnam-recognized test reports; calculations based on Chinese standards A: Investor
R: EPC Contractor / Designer
C: Fire Safety Consultant
Geotechnical & Foundation Borehole locations and depth; settlement and load verification per TCVN Insufficient investigation data; experience-based foundation selection A: Investor
R: EPC Contractor / Designer
C: Geotechnical Consultant
Permits & Approvals EIA – Fire Design Approval – Construction Permit sequence and milestones Treating approvals as parallel processes; unclear pre-construction conditions A: Investor
R: EPC Contractor / Consultant
C: Industrial Zone Authority / Regulators
Documentation & Acceptance Inspection records; hidden works acceptance; variations and as-built dossier Incomplete signatures and seals; loss of version control A: EPC Contractor
R: QA/QC Team
C: Supervision Consultant / Third Party

IV. Dong Hui’s Recommendation: Integrating EPC to Align Approvals, Standards, Supply Chain, and Acceptance

  • Design Front-Loading: Conduct TCVN/QCVN clause verification and risk pre-review at the concept stage to produce “permit-ready drawings”.

  • Localized Supply Chain: Prioritize materials and equipment with established Vietnamese certification and testing pathways to avoid approval bottlenecks at acceptance.

  • Milestone-Driven Control: Embed permitting milestones into master schedules and contracts to ensure lawful commencement, approvable acceptance, and certifiable assets.

Conclusion

For investment in Vietnam, safety and compliance are the “1”, while returns are the “zeros” that follow. By converting the “three pitfalls” into three control gates, projects can achieve on-time commissioning, compliant operation, and orderly settlement.

If you require site selection consulting services, please click to contact DongHui’s Senior Consultant.

Address: Room 01, 3rd Floor, Luxury Park Views Building, Lot D32, Cau Giay New Urban Area, Cau Giay Ward, Hanoi, Vietnam

Tel: (+84) 332 685 000 – DGD. Zhang Yongfang

Email: donghui.2016@gmail.com